Fullerton
Station
943-47 W. Fullerton Ave.
Chicago, IL 60614 |
Station
Status: |
|
|
|
|
New Elevators Open at Brown Line Belmont and Fullerton Stations
|
Elevators Improve Accessibility |
|
The newly-installed elevators at CTA’s Belmont and Fullerton stations are now available for customers. The elevators at Fullerton opened on Thursday, December
31 and the elevators at Belmont began service as of Tuesday, December 29, 2009.
With the elevators at Belmont and Fullerton, a total of 91 out of the 144 CTA rail stations are accessible to customers with disabilities. All CTA buses and trains are accessible.
The elevators at Belmont and Fullerton were installed as part of the CTA’s larger $530 million Brown Line capacity expansion project, which is designed to increase capacity and accessibility and bring 18 stations along the line to a state of good repair.
Belmont and Fullerton are the last of 18 stations renovated through the project. The two stations have remained open during construction and they are scheduled to be fully complete by the end of 2009.
Renovations at the Brown Line Belmont and Fullerton stations include brighter lighting, tactile edging, Braille signs and wheelchair accessible turnstiles, an upgraded public address system and expanded platforms.
Read the complete press
release.
|
_____________________________________________________ |
_____________________________________________________ |
|
Fullerton Stationhouse Entrance Reopened |
|
Although construction work continues, on September 12, CTA customers entering and exiting the Fullerton station served by the Red, Brown and Purple lines began using the new permanent station entrance .
The temporary entrance was opened in October 2006 to allow crews to relocate the historic stationhouse to the north side of Fullerton Parkway and build the new station in its place.
Construction work associated with the Brown Line capacity expansion project will continue at Fullerton and in the new stationhouse until later this year. Upon completion of construction work, the Fullerton station will be fully accessible to customers with disabilities.
|
_____________________________________________________ |
|
CTA
Completes Three-Track Operation at Fullerton Station
|
|
As
of Saturday, November 22, 2008 at 5 a.m., construction is
completed on the southbound track at Fullerton and
service is available on both southbound tracks
signaling the end of three-track operation
during rush hour at Fullerton. Three-track operation
is still in place at Belmont.
Since March 30, southbound Brown, Red and Purple
Express trains have been limited to one southbound
track at Belmont and Fullerton while the platforms
are being rebuilt and tracks reconfigured to allow
room for the installation of elevators.
The restoration of normal southbound service at Fullerton
means trains can operate more freely south allowing
for smoother operation for Red, Brown and Purple Line
Express trains arriving at the station.
CTA expects to conclude the three-track operation
at Belmont by the end of the year. In May, CTA announced
that it was accelerating the three-track project in
order to restore the southbound track to service by
the end of 2008, six months earlier than previously
announced.
The first phase of three-track operation began Monday,
April 2, 2007. Red, Brown and Purple Express trains
shared one northbound track at Fullerton and Belmont.
Normal northbound service resumed in March 2008.
On an average weekday more than 13,000 Red, Brown
and Purple Express customers board at Fullerton. The
Brown Line is one of CTA's busiest rail lines, serving
more than 80,000 customers each weekday, with 19 stations
from Kimball on the north to the downtown Chicago Loop.
Read the complete press
release.
|
_____________________________________________________ |
CTA
to Accelerate Three-Track Work
|
Escalators
Added to Fullerton and
Belmont Renovations |
The construction work to realign the tracks at the Belmont
and Fullerton Brown Line stations will be accelerated,
allowing the CTA to restore the southbound
track to service by the end of 2008, six months
earlier than previously announced.
Southbound Brown, Red and Purple Express
trains have been limited to one southbound track at
Belmont and Fullerton since March 30 while the platforms
are being rebuilt and tracks reconfigured to allow
room for the installation of elevators at both stations.
As a result of three-track operation, CTA has supplemented
bus service near the stations and added personnel
and signage in an effort to assist affected customers.
In addition, the CTA announced that it
will add escalators to the Belmont and Fullerton stations.
The original plans provided space for future installation
of escalators but because the project remains within
its budget and on schedule the CTA has determined that
there are sufficient funds to install two escalators
at each station. The escalator installation is scheduled
to be completed by December 2009.
Read press
release. |
_____________________________________________________ |
Red,
Brown & Purple Express Trains
Share One Track |
Eight-Car
Trains Operate on Brown Line
During Rush Periods |
The
next phase of three-track
operation at the Belmont and Fullerton stations
has started.
Effective March 30, 2008, southbound trains are limited
to one track at the Belmont and Fullerton stations
due to construction for the Brown Line capacity expansion
project. To help ease the impact, the CTA is
operating eight-car trains on the Brown Line during
morning and evening rush hours. The introduction
of eight-car service has occurred nearly 18 months
earlier than originally planned.
Read more about three-track
operation. |
_____________________________________________________ |
Northbound
Red Line Trains
Resume Operation on Normal Track at Fullerton on Friday,
January 25 |
Northbound Red Line trains resumed operating
on the inner northbound track at Fullerton station,
track 3, on Friday, January 25, 2008. Construction
crews have completed northbound track work at Fullerton
so northbound Red Line trains will no longer have
to share tracks with northbound Brown and Purple Express
trains. Northbound Red Line customers have resumed
normal boarding and exiting at Fullerton.
Red, Brown and Purple Express trains have shared one
northbound track at Fullerton since April 2, 2007 while
the platform was rebuilt and tracks were reconfigured. (more) |
_____________________________________________________ |
Fullerton
Buses Reroute August 29-30
Due to construction at
the Fullerton station, #74 Fullerton buses will undergo
a reroute near the Brown/Red station on Wednesday, August
29 and Thursday, August 30 from 9:15
p.m. each evening until 5 a.m. the next
morning.
Buses will travel over the regular route to Sheffield
then will operate via Lincoln, Halsted, Webster, Sheffield
then return to Fullerton and resume the regular route.
|
Temporary Station Entrance at Fullerton Opens October 8
Reconstruction of the Fullerton station requires
CTA customers to use a temporary station entrance beginning
Sunday, October 8, 2006 as work continues to rebuild
the facility as part of the Brown Line capacity expansion
project.
Beginning Sunday, October 8 at 1 p.m., CTA customers
can access trains at Fullerton via the temporary station
entrance, which is located on the south side of Fullerton
Avenue approximately 70 feet east of the existing stationhouse.
The temporary station entrance will provide the same amenities as a regular station, including a Customer Assistant booth and farecard vending machines.
CTA buses that provide direct service to the Fullerton
station –
#11 Lincoln/Sedgwick and #74 Fullerton – are
not affected.
|
|
The
Renovated Fullerton Station |
|
Renovated Fullerton
station platform.
Click image for street level rendering illustrating
the future Fullerton station. |
|
|
The
renovated Fullerton station will benefit
all Brown Line customers with: |
|
|
• |
Accessibility
for everyone
Elevators and accessible
turnstiles meet Americans with Disabilities
Act requirements. |
• |
Modern and convenient features
Escalators and wider stairways to
improve platform access, more turnstiles
to ease congestion and additional
exits/entrances to improve the flow
of customer traffic. |
|
|
|
|