| |
 |
|
CTA
to Accelerate Three-Track Work to Restore Normal Operation
by End of 2008
|
Escalators
Added to Fullerton and Belmont Renovations
|
The construction work to realign the tracks at the Belmont
and Fullerton Brown Line stations will be accelerated,
allowing the CTA to restore the southbound
track to service by the end of 2008, six months earlier than previously
announced.
Southbound Brown, Red and Purple Express
trains have been limited to one southbound track at
Belmont and Fullerton since March 30 while the platforms
are being rebuilt and tracks reconfigured to allow
room for the installation of elevators at both stations.
As a result of three-track operation, CTA has supplemented
bus service near the stations and added personnel and
signage in an effort to assist affected customers.
In addition, the CTA announced that it will add escalators
to the Belmont and Fullerton stations. The original
plans provided space for future installation of escalators
but because the project remains within its budget and
on schedule the CTA has determined that there are sufficient
funds to install two escalators at each station. The
escalator installation is scheduled to be completed
by December 2009.
Read press
release. |
| ________________________________________________ |
Red,
Brown and Purple Express Trains Share One Track
|
Eight-Car
Trains Operate on Brown Line
During Rush Periods
|
The next phase of three-track
operation at the Belmont
and Fullerton stations has started.
Effective March 30, 2008, southbound trains are
limited to one track at the Belmont and
Fullerton stations due to construction for the Brown
Line capacity expansion project. To
help ease the impact, the CTA is operating
eight-car trains on the Brown Line during morning and
evening rush hours. The introduction of eight-car
service has occurred nearly 18 months earlier than
originally planned.
Paulina and
Wellington stations
closed for renovation on March 30. While
the stations are under construction, Brown Line trains
will bypass both stations.
Also on March 30, the CTA reopened the Southport station
and opened a temporary station at Diversey.
Both stations had been closed for construction and
are now able to accommodate eight-car trains. Using
a temporary station at Diversey makes it possible
to reopen for service nearly three months earlier than
originally planned. Work
to install elevators and complete the stationhouse
at Diversey will continue throughout the spring.
Read more about three-track
operation. |
| ________________________________________________ |
Addison Station Reopened; Irving Park Station Temporarily
Closed
|
|
The Addison Brown Line station reopened December
3, 2007 following work to lengthen platforms, rebuild
the stationhouse and make the station accessible.
Two newly installed elevators are now in operation
making the station accessible to all CTA customers.
With the completion of the renovations at Addison,
80 of CTA’s 144 rail stations are now accessible.
In addition to the new elevators, accessible features
also include: an accessible turnstile, tactile platform
edging, gap fillers, TTY telephones and Braille signs.
Also new to the station are two auxiliary exits,
one serving the northbound platform and one serving
the southbound platform. Other upgrades include wider
stairways, additional turnstiles, a new platform
canopy, customer assistant call buttons, an information
kiosk, heaters, benches, brighter lighting, windbreaks
and improved station and directional signs.
Irving Park station closed
temporarily on December 3, 2007. While the Irving
Park station is closed, customers may board the Brown
Line at the adjacent, newly-renovated Montrose or
Addison stations.
The Damen station
was temporarily closed on November
27, 2007 for up to 12 months. When the Damen
and Irving Park stations reopen they will both be newly
accessible to customers.
|
Montrose Station Reopened Nov. 26; Damen Temporarily
Closed
|
The
Montrose Brown Line station reopened on
November 26, 2007 following work to lengthen platforms,
rebuild the stationhouse and make the station accessible.
The station closed to customers last December for renovation
and re-opened six days ahead of schedule.
Two newly installed elevators
are now in operation making the station accessible
to all CTA customers. With the completion of the renovations
at Montrose, 79 of CTA’s 144 rail stations are
now accessible. In addition to the new elevators, accessible
features also include: an accessible turnstile, tactile
platform edging, gap fillers, TTY telephones and Braille
signs.
Other improvements to Montrose include a newly rebuilt
stationhouse, wider stairways, additional turnstiles,
a new platform canopy, customer assistant call buttons,
an information kiosk, heaters, benches, brighter lighting,
windbreaks and improved station and directional signs.
Damen is
the next Brown Line station scheduled to undergo renovation
and that station closed on November 26 for up to 12
months. While the Damen station is closed, customers
may board the Brown Line at the adjacent, newly renovated
Western or Montrose stations.
On December 3, CTA will
reopen the Addison station to customers and temporarily
close the Irving Park station for up to 12 months.
When the Damen and Irving Park stations reopen they
will both be newly accessible to customers.
|
| ________________________________________________ |
Montrose and Addison Stations to Reopen; Damen and Irving
Park Will Temporarily Close
|
On November 26, 2007, CTA will reopen the Montrose station
to customers and temporarily close the Damen station
for up to 12 months.
On December 3, 2007, the CTA will
reopen the Addison station
and temporarily close the Irving
Park station for up to 12 months.
Both
Montrose and Addison have been closed to service
since December 2006. When the stations reopen
they will both be newly accessible to customers.
While the Damen station
is closed, customers may use the adjacent Brown Line
stations at Western and
Montrose. While
the Irving Park station
is closed, customers may use the Montrose and Addison stations.
|
| ________________________________________________ |
Sedgwick Station Entrance Reopens on
November 12
|
The Sedgwick station entrance reopened on Monday,
November 12, 2007.
The newly renovated station entrance is accessible
to customers with disabilities and includes these
customer-friendly features:
- New elevators
- Brighter lighting
- Refurbished canopies
- Renovated and expanded historic station entrance
- Benches
- Bike racks
- Longer platforms
The station has remained open to customers throughout
construction. The temporary entrance located
on Hudson is no longer in use. |
| ________________________________________________ |
Temporary Station Entrance Opened at Chicago Avenue
Station on October 15
|
The entrance to the Chicago Avenue Brown Line station
temporarily
relocated one block south of
the existing entrance to Superior and Franklin at
5 a.m. Monday, October 15, 2007 as CTA continues
work to rebuild the Chicago
Avenue station
and extend platforms as part of the Brown Line capacity
expansion project.
Customers use new stairways to the elevated
platforms at the temporary entrance to access Purple
Line Express and Brown Line trains. The temporary
entrance provides the same amenities as the existing
entrance, including farecard vending machines. The
temporary entrance is expected to be in place through
spring 2008.
|
| ________________________________________________ |
New Northbound Track and Platform at Belmont
Station Placed into Service on August 9
|
Crews placed the newly constructed northbound
platform and tracks into service at the Belmont Brown/Red/Purple
Express station at 10 p.m. Thursday, August 9, 2007.
The new platform and tracks are located east of the
current platform and tracks. Customers will board
northbound Red, Brown and Purple Line Express trains
on the east side of the new
northbound platform.
|
| ________________________________________________ |
Armitage Brown Line Station Entrance Temporarily
Relocated
|
On Monday, July 23, 2007 at 5 a.m., the Chicago
Transit Authority temporarily relocated the entrance
to the Armitage station on the Brown Line. The new
temporary entrance is on the south side of Armitage
- across the street from the existing entrance. The
turnstiles, farecard vending machines and temporary
customer assistant kiosk are available in the
new temporary station entrance as well.
The temporary entrance is expected to be in place
until early 2008 while CTA continues work to rebuild
the Armitage station and extend platforms.
CTA’s #73 Armitage bus, which provides
direct service to the Armitage station, is
not affected.
|
| ________________________________________________ |
Diversey Brown Line Station Temporarily Closed on June
25 for Renovation
|
On
Monday, June 25, 2007, the Diversey station on the
Brown Line temporarily closed for 12 months while
construction crews work to upgrade and extend platforms,
rebuild the station house and make the station accessible
to customers with disabilities. The adjacent stations – Wellington
and Fullerton – remain open during the
temporary closure of the Diversey station so customers
may continue to use them to access Brown Line service.
Improvements to the Diversey station will include
a new stationhouse, elevator access to each platform,
a wheelchair accessible turnstile, longer platforms
to accommodate eight-car trains instead of the current
six-car trains, security cameras, brighter lighting,
tactile edging on the platforms and an upgraded public
address system.
The Diversey station is located in an area where
existing CTA service is plentiful. In addition to
nearby rail stations, there are six existing CTA
bus routes that provide service near Diversey station
on weekdays and weekends, the #8 Halsted, #11 Lincoln/Sedgwick,
#22 Clark, #36 Broadway, #74 Fullerton and the #76
Diversey. (Read
more)
|
| ________________________________________________ |
CTA Updates Three-Track Service Plan Providing
More Brown Line Service During Rush Periods
|
After evaluating travel patterns, ridership and
service over the past six weeks of three-track operation,
CTA President Ron Huberman said today that both bus
and rail ridership have increased compared to pre-three
track levels. Rail service has performed well through
the construction zone and the signaling systems have
been accommodating trains as planned, with capacity
for additional trains to be added back into operation.
As a result, a total of seven Brown Line trains—three
in the morning and four in the evening--have been
added
back to the schedule and adjustments will be
made to bus service beginning tomorrow to support
routes that have experienced the most ridership growth.
Read more here
|
| ________________________________________________ |
Three-Track Operation Begins April 2 at Belmont and Fullerton
Stations
|
Effective Monday, April 2, 2007, Red, Brown and
Purple Express trains are operating on three tracks
instead of four at the Belmont and Fullerton stations
on the City’s North Side.
Although trains will continue to stop at the stations
during three-track operation,
one of the four tracks along the platforms at each
station must be taken out of service while the platform
is rebuilt and tracks are reconfigured to allow room
for elevators to be installed. The specific track to
be taken out of service will vary during the course
of the project.
The construction is a phase of the Brown Line capacity
expansion project which, when completed at end of 2009,
will allow the CTA to accommodate more customers in
this busy and growing corridor and will make all Brown
Line stations accessible to people with disabilities.
Three-track operation web
page
|
| ________________________________________________ |
Southport Station Temporarily Closes on April 2 for Renovation
|
On Monday, April 2, 2007 the Southport station on
the Brown Line temporarily closed for renovation.
The Southport station is temporarily closed for 12
months while construction crews work to upgrade and
extend platforms, rebuild the station house and make
the station accessible to customers with disabilities.
The adjacent stations – Paulina and Belmont – are
open during the temporary closure of the Southport
station so customers may continue to use them to
access Brown Line service.
Improvements to the Southport station will include
a new station house, an elevator, a wheelchair accessible
turnstile, a longer platform to accommodate eight-car
trains instead of the current six-car trains, security
cameras, brighter lighting, tactile edging on the platform
and an upgraded public address system.
The Southport station is located in an area where
existing CTA service is plentiful. In addition to nearby
rail stations, there are five existing CTA bus routes
that provide service near Southport station on weekdays
and weekends, the #9 Ashland, #11 Lincoln/Sedgwick,
#22 Clark, #77 Belmont, #152 Addison and the #X9 Ashland
Express (weekdays until 7 p.m.). (Read
more) |
| ________________________________________________ |
Francisco station reopened on
Friday, March 9
|
The Francisco station reopened on Friday, March
9, 2007.
A major portion of the reconstruction has been completed
at Francisco including the complete rebuild of the
historic station house and installation of a ramp
which now makes the station accessible. Along
with a wheelchair accessible turnstile and tactile
edging on the platform, additional customer amenities
include brighter lighting, windbreaks, security cameras,
benches and a new public address system.
Construction crews will continue to work in the weeks
ahead to complete construction even after the station
opens for service. Additional work includes installing
permanent station signs, original artwork, windows and
continuing work to build a new auxiliary entrance at
Sacramento on the west end of the station. (read
more)
|
| ________________________________________________ |
Fullerton Station - New Northbound Platform and Boarding
|
A new northbound platform and tracks have been built
at the Fullerton station. The new platform and tracks
are located east of the current platform and tracks.
As a result, customers will board northbound trains
slightly differently.
Brown and Purple Express trains will use the new track
and customers will board from the newly constructed
platform. Customers should board trains on the
east side of the new northbound platform.
The existing northbound platform will continue to
be used for boarding northbound Red Line trains only.
Customers should board trains on the west side of the
platform.
Boarding for southbound trains will not be affected.
The new platform connects to the old platform so customers
will continue to have an accessible transfer between
Red, Brown and Purple Express trains. (read
more) |
| ________________________________________________ |
Kimball Station Reopened January 12 |
The Kimball station on the Brown Line reopened to
rail service at 4 a.m. on Friday, January 12, 2007.
A major portion of the reconstruction has been completed
at Kimball including brighter lighting, installation
of heaters and windbreaks, new benches and an information
kiosk.
Construction crews will continue to work in the weeks
ahead to complete construction even after the station
opens for service. Additional work includes installing
permanent station signs, security cameras, original artwork,
windows, canopies and continuing work to complete the
extension of the platform. (read
more) |
| ________________________________________________ |
Montrose and Addison Stations Temporarily Closed on December
2 |
On Saturday, December 2, 2006 at 3 a.m. the Montrose
and Addison stations on the Brown Line temporarily
closed for renovation. Both the Montrose and Addison
stations will temporarily close for 12 months while
construction crews work to upgrade and extend platforms,
rebuild the station house and make the station accessible
to customers with disabilities. The adjacent stations – Paulina,
Irving Park and Damen – will remain open during
the temporary closure of the Montrose and Addison
stations so customers may continue to use them to
access Brown Line service.
Improvements at both the Montrose and Addison stations
will include new station houses, new elevators and
wheelchair accessible turnstiles, longer platforms
to accommodate eight-car trains instead of the current
six-car trains, security cameras, brighter lighting,
tactile edging on the platforms and upgraded public
address systems.
Both Montrose and Addison are located in areas where
existing CTA service is plentiful. In addition to nearby
rail stations, there are seven existing CTA bus routes
that provide service near Montrose station on weekdays
and weekends, the #78 Montrose, #50 Damen, #145 Wilson/Michigan
Express, #80 Irving Park, #X80 Irving Park Express,
#81 Lawrence and the #148 Clarendon/Michigan Express
(weekdays, peak direction only).
Eight existing CTA bus routes provide service near
Addison station, the #152 Addison, #9 Ashland, #X9
Ashland Express (weekdays only), #11 Lincoln/Sedgwick,
#50 Damen, #77 Belmont, #80 Irving Park and the #X80
Irving Park Express. (read
more)
|
| ________________________________________________ |