The Brown Line Capacity Expansion Project was a multi-year endeavor. As of December 31, 2009, all 18 renovated stations have been completed.

With the installation of the elevators at Bemont and Fullerton, 91 of CTA's 144 rail stations are now accessible.

 

Progress Chart as of December 2009



 

 

 

MY STATION
As of
kimball brownline complete
kedzie brownline complete
Francisco complete
Rockwell complete
Western complete
Damen closure
Montrose complete
Irving Park closure
Addison complete
Paulina paulina status
Southport closure
belmont belmont status
Wellington blank
Diversey closure
Fullerton blank
Armitage blank
sedgwick complete
Chicago blank
 